Case Studies

Date: July 24, 2016
Locations: Columbus, Georgia
Contractor: Engineered Solutions

Project Scope:
Concrete Bridge to be reinforced for traffic. Small concrete beams were under designed.

GA bridge GA bridge

Solution: One layer 600 gsm carbon fiber with carbon anchors were installed to achieve this.

GA bridge GA bridge

Conclusion: Testing of Anchors prove to dramatically increase long term creep of the surface mounted carbon fiber under the flexural load. Project was completed in 2 days.

GA bridge GA bridge