Fortec
Fortec Stabilization Systems
Carbon Fiber Technologies
Questions? Call Us
1-800-207-6204

Versión de Español
Case Studies

Date: July 24, 2016
Locations: Columbus, Georgia
Contractor: Engineered Solutions

Project Scope:
Concrete Bridge to be reinforced for traffic. Small concrete beams were under designed.

GA bridge GA bridge

Solution: One layer 600 gsm carbon fiber with carbon anchors were installed to achieve this.

GA bridge GA bridge

Conclusion: Testing of Anchors prove to dramatically increase long term creep of the surface mounted carbon fiber under the flexural load. Project was completed in 2 days.

GA bridge GA bridge





HOME | ENGINEERING TIPS & DESIGN | PRODUCTS & SPECIFICATIONS | PROJECTS & CASE STUDIES | ABOUT Fortec | CONTACT FORTEC


Fatal error: Call to undefined function mysql_connect() in /home/fortecst/public_html/counter/mysql.class.php on line 23