Date: April 22, 2010
Location: Teatro-Verde historical building. Toronto, Ontari,o Canada
Contractor: Basement Technologies Inc ON
Engineer: Saberas Engineering
Material Used: Fortec 600gsm Unidirectional Carbon Fabric w/1276 epoxy resin
Project Scope:
The Fašade of building was desired to be preserved, while structure / building was in need of replacement. Carbon fiber was used to hold fašade together as existing structure was removed. After new structure was completed the fašade was moved into place to meet building.

Foundation Repair


Conclusion:
The carbon fiber allowed for the removal of building without experiencing any major cracking of fašade, thus preserving the historical value of the fašade.

Foundation Repair Foundation Repair





HOME | ENGINEERING TIPS & DESIGN | PRODUCTS & SPECIFICATIONS | PROJECTS & CASE STUDIES | ABOUT Fortec | CONTACT FORTEC

© Copyright 2010 Fortec Stabilization Systems
All Rights Reserved.

Fortress Stabilization products are protected by the following patents: 7,823,354 (Structure reinforcement system); 7,743,585 (Structure reinforcement system); RE39,839 (Carbon Fiber reinforcement system); 6,846,537 (Carbon fiber reinforcement material); 6,746,741 (Carbon Fiber reinforcement system); 6,692,595 (Carbon Fiber reinforcement Systems); and other pending patents.

This website is valid HTML 4.01 Transitional in compliance with W3C